Timpanogos Special Service District (TSSD)
Pile Driving Project
Background
The Timpanogos Service District (TSSD) is committed to ensuring reliable wastewater treatment and protecting water quality for our community. As part of ongoing facility upgrades, we will be conducting pile driving work at 6400 N 5050 W to support critical infrastructure improvements.
Schedule
April 3 – May 10, 2025
June 15 – October 31, 2025
Work Hours
Monday – Saturday, 7:00 AM – 6:00 PM
Process
A total of 538 steel piles, each 120 feet deep, will be driven using a large hydraulic hammer.
Impacts
This work will generate significant noise, which may be heard in surrounding areas. We appreciate your patience and understanding as we complete this important work.
Stay Current
Be sure to check out the Updates Page for the latest information on what is happening with the project!

Why This Work Matters
This pile driving is essential for the foundation of new infrastructure that will enhance wastewater treatment capacity and efficiency, ensuring continued protection of public health and the environment.
Stay Informed
We encourage you to sign up for the email updates that will provide information about the expected impacts for the coming week. Just send an email to: tssdpilesproject@gmail.com and write “Updates” in the subject line.
Contact Us
Hotline 800-945-2744